Design Schedule
Mirror Lake Condominium
Schedule is based on a December 1, 2026 Notice to Proceed and the phase durations outlined in the RFP. Durations for each phase may be accelerated. Subject to change; CPH will follow the Architect’s timeline.
2026
2027
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Conceptual Design
Underway
Schematic Design
3 Months
Design Development
4 Months
Construction Documents
4 Months
Permitting / Pricing
Ongoing · Nov 2027
Sales Gallery Design
3 Months
Gallery Build Out
Opens 8/2/27 · 4 Months from Approved Drawings
Schematic Design
Dec 2026 – Feb 2027
12/1/26
Notice to Proceed + SD Kickoff
12/8/26
Programming + Unit Mix
1/15/27
50% SD Package to Owner
1/22/27
Owner Comments to Design Team
2/26/27
100% SD Package to Owner
Design Development
Mar 2027 – Jun 2027
3/1/27
DD Kickoff
3/12/27
Owner Comments on 100% SD
4/16/27
50% DD Package to Owner
4/30/27
Owner Comments to Design Team
5/14/27
Finish + Lighting Selections
6/25/27
100% DD Package to Owner
Construction Documents
Jul 2027 – Oct 2027
7/6/27
CD Kickoff
7/16/27
Owner Comments on 100% DD
8/20/27
50% CD Internal Coordination
8/27/27
Site / Foundation Permit Set
9/17/27
90% CD Package to Owner
10/1/27
Owner + GC Comments
10/29/27
100% CDs Issued for Permit
Sales Gallery
Jan 2027 – Aug 2027
1/4/27
Sales Gallery Design Kickoff
2/5/27
Gallery Concept + Finishes
3/5/27
Gallery Drawings to Owner
3/26/27
Approved Gallery Drawings
4/1/27
Gallery Build Out Begins
7/30/27
Build Out Complete + Punch
8/2/27
Sales Gallery Opens
Bold items indicate key owner deliverables and permit submissions. Gallery build out assumes 4 months from approved drawings.