Construction Schedule

Mirror Lake Condominium

+/- 36 month construction duration following the design phases, with an early site / foundation permit and multiple phased TCOs assumed.

2027

2028

2029

2030

Project Overview

Design · SD / DD / CD · 11 Months
Construction · +/- 36 Months

2027

2028

2029

2030

Q1

Q2

Q3

Q4

Q1

Q2

Q3

Q4

Q1

Q2

Q3

Q4

Sitework / Foundations

Nov 27 – Jun 28

Structure

Apr 28 – Jun 29

Building Enclosure

Dec 28 – Mar 30

MEP Infrastructure

Sep 28 – May 30

Interior Fit Out

Jun 29 – Aug 30

Commercial Space Delivery

Feb 30 – Jul 30

Amenity Delivery

Mar 30 – Sep 30

Commissioning

May 30 – Oct 30

Design Team CA

Construction Administration

Final Completion / TCO

TCO 1

TCO 2

C of O

Multiple TCOs · Final C of O Oct 2030

Construction sequencing shown is preliminary and will be refined with the Owner and General Contractor.