Construction Schedule
Mirror Lake Condominium
+/- 36 month construction duration following the design phases, with an early site / foundation permit and multiple phased TCOs assumed.
2027
2028
2029
2030
Project Overview
2027
2028
2029
2030
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Sitework / Foundations
Nov 27 – Jun 28
Structure
Apr 28 – Jun 29
Building Enclosure
Dec 28 – Mar 30
MEP Infrastructure
Sep 28 – May 30
Interior Fit Out
Jun 29 – Aug 30
Commercial Space Delivery
Feb 30 – Jul 30
Amenity Delivery
Mar 30 – Sep 30
Commissioning
May 30 – Oct 30
Design Team CA
Construction Administration
Final Completion / TCO
TCO 1
TCO 2
C of O
Multiple TCOs · Final C of O Oct 2030
Construction sequencing shown is preliminary and will be refined with the Owner and General Contractor.